Julius v. Accurus Aerospace Corp.

Court of Chancery of Delaware

October 31, 2019

BRADLEY E. JULIUS, in his capacity as Seller Representative, Plaintiff,
v.
ACCURUS AEROSPACE CORPORATION and ACCURUS AEROSPACE WICHITA LLC (f/k/a ZTM Acquisitions, LLC, f/k/a ZTM Aerospace, LLC), Defendants. ACCURUS AEROSPACE CORPORATION and ACCURUS AEROSPACE WICHITA LLC (f/k/a ZTM Acquisitions, LLC, f/k/a ZTM Aerospace, LLC), Counterclaim-Plaintiffs,
v.
ZTM, INC. (n/k/a BKJ Holdings, Inc.), THE KELLEY JULIUS REVOCABLE TRUST, THE BRADLEY JULIUS REVOCABLE TRUST, and BRADLEY E. JULIUS, in his capacity as Seller Representative, Counterclaim-Defendants.

          Date Submitted: July 11, 2019

          Lisa Zwally Brown, GREENBERG TRAURIG, LLP, Wilmington, Delaware; Paul D. Brown and Stephanie S. Habelow, CHIPMAN BROWN CICERO & COLE, LLP, Wilmington, Delaware; Lynn D. Preheim and Christina J. Hansen, STINSON LEONARD STREET LLP, Wichita, Kansas, Attorneys for Plaintiff Bradley E. Julius and Counterclaim-Defendants, ZTM, Inc., The Kelly Julius Revocable Trust, The Bradley Julius Revocable Trust, and Bradley E. Julius.

          Raymond J. DiCamillo, Kevin M. Gallagher, Sara C. Hunter, and Ryan D. Konstanzer, RICHARDS, LAYTON & FINGER P.A., Wilmington, Delaware; Thad J. Bracegirdle and Andrea Schoch Brooks, WILKS, LUKOFF & BRACEGIRDLE, LLC, Wilmington, Delaware; Adam H. Offenhartz, Peter M. Wade, David F. Crowley-Buck, and Lauren M. Kobrick, GIBSON, DUNN & CRUTCHER LLP, New York, New York, Attorneys for Defendants and Counterclaim-Plaintiffs Accurus Aerospace Corporation and Accurus Aerospace Wichita LLC.

          MEMORANDUM OPINION

          ZURN, VICE CHANCELLOR.

         This case, concerning an acquisition in the aviation parts industry, teaches an important lesson about the benefits of allocating risk among contracting parties and detriments of imprecise drafting. The buyers considered this acquisition in a niche industry to be very lucrative. The sellers produced parts for a particularly important customer: the world's largest aerospace company, The Boeing Company.

         Boeing parts generated significant revenue for the company. At the time of contracting, all parties knew the sellers' contracts for dozens of high-revenue Boeing parts expired at the end of 2016. This was a common occurrence in the industry, and it was typical for parts to be added to and removed from the sellers' master contract with Boeing. On most occasions, Boeing would request a quote for expiring parts and afford the sellers the opportunity to re-bid on those parts.

         Throughout the due diligence process and at the time of closing, both the buyers and sellers believed in good faith that Boeing would give the company the opportunity to re-bid on all parts expiring at the end of 2016, as Boeing had done for other expiring parts in the past. Aware of the value derived from producing these parts, the buyers elected to pursue the acquisition. The deal closed, and the parties placed a portion of the purchase price in an escrow fund, anticipating the possibility of litigation.

         Though there was no guarantee the company would win the Boeing contracts, the buyers walked into a situation that was worse than they expected. Months after the acquisition, the buyers learned Boeing never requested quotes for dozens of parts under the expiring contracts. Much to the buyers' dismay, Boeing awarded those contracts to other suppliers in 2013 and 2014 and, therefore, the company had "lost" the opportunity to bid on those parts at that time. The buyers do not allege that, at the time of contracting, the sellers knew these parts would be unavailable for re-bid.

         Seeking redress for the lost bid opportunity, the buyer refused to consent to release the escrow funds. The sellers filed suit to obtain those funds. The buyers counterclaimed, alleging breaches of representations and warranties in the governing asset purchase agreement. The parties filed cross-motions for partial summary judgment on the issue of liability on all counts brought by all parties. For the reasons explained below, I find that the sellers are entitled to summary judgment on the buyers' counterclaim and that the buyers are entitled to summary judgment on the sellers' affirmative claims.

         I. BACKGROUND

         Plaintiff Bradley E. Julius brings five affirmative claims for relief, in his capacity as Seller Representative, on behalf of BKJ Holdings, Inc. (f/k/a ZTM, Inc.) ("ZTM" or the "Company"), the Bradley E. Julius Revocable Trust, the Kelly Julius Revocable Trust, Kelly E. Julius, and himself (collectively, "Sellers"). In response, Defendants Accurus Aerospace Corporation and Accurus Aerospace Wichita LLC (f/k/a ZTM Acquisitions, LLC, f/k/a ZTM Aerospace, LLC) (collectively, "Accurus" or "Buyers") assert a counterclaim against Sellers. The parties have filed cross-motions for summary judgment on all claims, so I draw the facts from the evidentiary record developed by the parties.[1]

         A. ZTM Succeeds In The Aviation Parts Industry, And Boeing Becomes ZTM's Most Valuable Customer.

         Julius founded ZTM, which he owned and controlled as Trustee of the Bradley E. Julius Revocable Trust, together with Kelly Julius as Trustee of the Kelly Julius Revocable Trust.[2] ZTM operated out of Wichita, Kansas, one of the key aerospace supply regions in the United States.[3] ZTM manufactured large, complex precision aerospace parts and assemblies for major commercial aviation and military customers.[4] By 2015, ZTM had grown to a business of 126 employees with over $35 million in anticipated revenue.[5] ZTM's primary customer was The Boeing Company ("Boeing"), which accounted for more than half of its sales.[6] In 2014, revenue from Boeing-related entities comprised 66.3% of ZTM's sales.[7] ZTM projected that by 2016, Boeing-related entities would account for 70.3% of ZTM's sales.[8]

         The relationship between ZTM and its customers, such as Boeing, followed an industry-standard pattern. Airplane parts manufacturers typically enter into a Long Term Agreement ("LTA"), or "master contract," with customers like Boeing.[9]That LTA establishes the terms on which the supplier will manufacture parts for the customer.[10] The LTA often contains separate sub-contracts for specifically identified parts, which may expire before the LTA does.[11] ZTM and Boeing entered into a master contract that included sub-contracts for certain Boeing parts.[12] Some of those contracts were set to expire at the end of 2016, before the master contract's expiration date.[13]

         Suppliers can bid on sub-contracts to manufacture parts.[14] When Boeing bids out parts, it typically sends a Request for Proposal ("RFP") or Request for Quotation ("RFQ") to the supplier.[15] After receiving the RFQ or RFP from manufacturers like ZTM, Boeing determines which manufacturer wins the contract, and sends that manufacturer an award letter.[16]

         The award letter identifies the specific parts Boeing has awarded to the manufacturer.[17] Via amendment, those parts "roll on" or are added to the master contract.[18] But if the manufacturer bid for parts under an expiring contract and Boeing decided to award those expiring parts to another company, then the expiring parts would "roll off" of the master contract at their expiration date.[19] ZTM maintained master electronic files on its internal system that contained all RFQs, RFPs, award letters, and related documents.[20]

         Manufacturing parts for Boeing through this process was the "bread and butter" of ZTM's business.[21] Although winning a contract renewal bid with Boeing was not guaranteed, the opportunity to re-bid on existing contracts was "critical to the success of [ZTM]"[22] and was the "lifeblood" of the Company.[23] ZTM vigorously pursued the opportunity to re-bid on expiring contracts.[24]

         For example, the Company proactively reached out to Boeing to secure such opportunities in 2015.[25] In the summer and fall of 2015, ZTM received four RFQs offering the opportunity to bid to renew parts that were expiring at the end of 2015.[26]ZTM received an award letter in December 2015 for those RFQs.[27] Upon receiving that award letter, Jamie Woodson, ZTM's business manager, identified parts for which ZTM was not provided the opportunity to re-bid, and contacted Boeing for an explanation.[28] The value of those parts was approximately $2 million in sales in 2015.[29] Similarly, upon learning in 2015 that Boeing was offering the opportunity to re-bid on certain parts expiring in 2016 and 2017, Julius and Woodson contacted Boeing and took immediate steps to secure ZTM's ability to re-bid on those parts.[30]

         B. Julius Decides To Sell ZTM.

         Rowan Taylor founded Liberty Hall Capital Partners, L.P ("Liberty") in 2011. Liberty is a private equity firm focused exclusively on investments in the aerospace industry.[31] Liberty formed Accurus in November 2013, [32] and continues to control Accurus through an affiliate.[33] Accurus is a buyer of aerospace manufacturing companies. Liberty, either independently or through Accurus, acquired six aerospace companies prior to acquiring ZTM.[34]

         In 2015, Julius decided to sell ZTM. He hired Koch Siedhoff Hand & Dunn, LLP ("Koch") to assist with the sale.[35] During the sale process, ZTM marketed itself as the "second largest interior shop for Boeing Commercial."[36] In August 2015, ZTM's broker, Ed Dunn, approached Accurus about a potential sale of ZTM's assets, property, and rights.[37] Dunn sent an executive summary of the opportunity to Liberty.[38]

         On behalf of Liberty, Taylor signed a confidentiality agreement with ZTM dated August 13, 2015 (the "Confidentiality Agreement").[39] Under the Confidentiality Agreement, Liberty received "Evaluation Materials" in order to evaluate a possible transaction with ZTM.[40] The Confidentiality Agreement defines "Evaluation Materials," in part, as

all information, in whatever form or format and however it may be embodied, concerning the Disclosing Party that are furnished, made available, or otherwise disclosed to a Receiving Party by or on behalf of the Disclosing Party, orally or in writing, and whether or not such Evaluation Materials in whole or in part are protectable trade secrets independent from this Agreement; and includes the business plans, historic financials, projected financials, PowerPoint presentations, software, contracts, agreements, understandings, notes, analyses, compilations, studies or other documents or materials whether prepared by any Party or others, which contain or reflect all or any portion of such materials.[41]

         In the Confidentiality Agreement, Liberty and ZTM agreed, "[T]he other Party does not make any representation or warranty as to the accuracy or completeness of such other Party's Evaluation Materials."[42]

         After signing the Confidentiality Agreement, Accurus determined that the timing was not right for Accurus to make an acquisition.[43] ZTM then struck a deal with another buyer, but that deal fell through.[44] Thereafter, Dunn contacted Liberty and Accurus again in early 2016.[45] Liberty and ZTM re-engaged the sale process and signed a new confidentiality agreement that was substantially similar to the previous agreement.[46]

         Sometime before March 2, ZTM began producing documents for Liberty to review to evaluate the ZTM acquisition.[47] As part of Buyers' due diligence, ZTM prepared spreadsheets of projections for Buyers to review, which included information on the airplane part numbers under contract, part quantities, the contract expiration dates, pricing, gross margins, sales, projected sales, and other financial information.[48] Woodson prepared the projections under the direction of Dunn and Arthur Hoopes of Koch.[49]

         In an email dated March 2, Liberty requested ZTM's revised forecasts for 2016 through 2019.[50] On March 4, on behalf of Sellers, Dunn sent several documents to Taylor and Jim Gibson, Accurus's Chief Executive Officer, including revised sales projections for 2016 through 2019.[51] Gibson "heavily relied" on these projections during due diligence.[52] In a letter dated March 11, Liberty, on behalf of Accurus, offered to purchase ZTM for $80 million.[53]

         On March 16, Dunn notified Liberty that ZTM discovered a formula error that affected the sales projections, which caused a swing of approximately $1.9 million in revenue.[54] Sellers corrected the error and circulated revised projections on March 16.[55] The parties did not circulate any additional revised forecasts.[56] Liberty did not revise its offer to purchase ZTM.[57]

         The projection spreadsheets included tabs specific to Boeing airplane models that listed each part number that ZTM was manufacturing.[58] Within each tab, ZTM identified parts for which it would not have the opportunity to re-bid when their contracts expired.[59] If a part was no longer available for re-bid, it was marked with a red triangle to alert Buyers of the expiring contract without the opportunity to re-bid.[60] Projections for parts marked with the red triangle indicated no future sales.[61]All parts without the red triangle were presented as available for re-bid, with sales projected through 2019.[62] The forecasts also included the gross margins for each part number.[63] Sellers "believed at the time the forecast spreadsheets were created that the prospective buyer would have the opportunity to bid on [certain parts expiring at the end of 2016]."[64]

         After due diligence began but before the parties executed the APA on June 3, ZTM communicated with Boeing about parts expiring at the end of 2016 and new parts, and provided Buyers with information regarding those communications.[65] For example, on March 2, Woodson emailed Boeing with a list of expiring parts, stating: "Below is the list of parts we were discussing yesterday that were on the RFQs that extended 2015 but are expiring in 2016 that we were told we lost. If there is an opportunity to re-bid these we would be very interested in fighting to keep this work at ZTM."[66] The parts referred to in the March 2 email were marked with a red triangle in the projections because ZTM did not secure contracts for those parts and understood they would not result in future revenue.[67] Boeing continued to award parts to ZTM during this period.[68] ZTM alerted Buyers of the newly awarded parts, and Buyers analyzed how these awards affected the projections.[69]

         During this period, Buyers and their consultants also sought part information from ZTM[70] and specifically requested that ZTM clarify the status of parts identified in the projections.[71] For example, on February 19, Hoopes emailed Dunn regarding a "write up of 2015 Follow on and 2016 expiring parts," and stated that "ZTM has a large number of Boeing parts that are due to expire at the end of 2016 [and] ZTM has already quoted on 212 of the 608 parts."[72] The revenue for the expiring parts in that email as expiring was not included in the March projections.[73]

         As Liberty's primary negotiator with responsibility for reviewing the APA, Taylor knew prior to executing the APA that certain Boeing parts were expiring at the end of 2016, and that there was no guarantee that Accurus would win a bid to continue manufacturing expiring parts.[74] ZTM informed Accurus that they believed the Company would have the opportunity to bid on the expiring parts.[75] As Julius testified: "At the time of the sale . . . everybody thought the opportunity to quote [the expiring parts] would come."[76] However, ZTM "never promised those parts to Accurus or Liberty."[77]

         C. Accurus Purchases ZTM Pursuant To The APA.

         Accurus purchased ZTM's assets pursuant to an Asset Purchase Agreement executed on June 3, 2016 (the "APA").[78] The deal closed on July 29 (the "Closing"). The APA contains an integration clause that states: "The Transaction Documents constitute the entire agreement and understanding of the Parties and supersede all prior agreements, undertakings, negotiations, and communications, both written and oral, among the Parties, or any of them, with respect to the subject matter hereof."[79] The APA defines "Transaction Documents" as "this Agreement, the Escrow Agreement, the Bill of Sale, the Assignment and Assumption Agreement, the Consulting Agreement, the Employment Agreements and the certificates, affidavits, and releases required to be delivered under this Agreement."[80]

         The APA also contains a number of representations and warranties. Section 3.25(d) states: "Seller has disclosed to Buyer any material disputes, complaints, or issues with respect to any customers or suppliers and the manner in which Seller proposes to resolve such disputes, complaints or issues."[81] Section 3.25(a) states:

Since the Balance Sheet Date, no customer, distributor, or supplier of the Business has terminated or materially reduced or altered its business relationship with Seller or Seller Subsidiary or materially changed the terms on which it does business with either, or threatened that it intends to cancel, terminate, or otherwise materially reduce or alter its business relationship with either.[82]

         Likewise, Section 3.7(a) states:

Since the Balance Sheet Date, the Seller Group has conducted its operations in the ordinary and usual course of business consistent with past practice, and there has not been any: (a) event, occurrence, or development that has had, or reasonably could be expected to have, individually or in the aggregate, a Material Adverse Effect.[83]

         The APA defines the Balance Sheet Date as December 31, 2015. Finally, Section 3.28 states:

No representation or warranty made by Seller in this Agreement and no statement contained in the Disclosure Schedule to this Agreement or any certificate or other document furnished or to be furnished to Buyer pursuant to this Agreement, including the other Transaction Documents, contains any untrue statement of a material fact, or omits to state a material fact necessary to make the statements contained therein, in light of the circumstances in which they are made, not misleading.[84]

         The APA does not include an explicit representation or warranty as to the accuracy of the projections Sellers shared with Defendants prior to entering into the APA. The parties did not attach ZTM's sales projections to the APA. The APA does not reference the sales projections, nor does it incorporate them by reference. Nor does the APA guarantee that Buyers would be able to renew expiring parts, or even that Boeing would allow Buyers to bid on such parts.

         The APA also establishes procedures the parties can follow in the event Buyers breached the APA's representations and warranties. Section 8.3(a)(i) of the APA states that ZTM must indemnify Accurus against any losses arising out of, relating to, or resulting from the breach of any ZTM representation or warranty, "without giving effect to any materiality, Material Adverse Effect or similar qualifications."[85] The APA includes procedures and standards the parties must follow to bring a "Direct Claim" for indemnification under the APA for breach of contract or otherwise.[86]

         Under the terms of the APA, Buyers deposited funds with an escrow agent for the exclusive purpose of satisfying Accurus in the event Accurus suffered indemnifiable losses (the "Indemnity Escrow Amount").[87] Pursuant to the APA, the parties entered into a separate Escrow Agreement on July 28, 2016.[88] Bank of America, National Association Global Custody and Agency Services, as escrow agent, agreed to hold the $3 million escrow amount in an escrow fund.[89] The Escrow Agreement echoes the APA's procedures and standards.[90]

         D. The Buyers Discover The Lost Parts.

         After the Closing, Boeing sent the Company an award letter, completing a bidding cycle that began with an RFQ Boeing issued before the acquisition.[91]Buyers compared the parts in the award letter with ZTM's projections provided during due diligence.[92] Buyers discovered 53 parts included on ZTM's projections under contracts expiring at the end of 2016, and identified as available for rebid, were not on the award letter (the "Lost Parts").[93] The revenue from the Lost Parts represented approximately 10% of ZTM's total projected sales from 2017 through 2019: $3.96 million in 2017, and $4.62 million in 2018 and 2019.[94]

         Boeing had awarded the Lost Parts to other suppliers before December 15, 2015, and as early as 2013 and 2014.[95] Sellers were not aware that Boeing had awarded the Lost Parts to other suppliers prior to the acquisition; Buyers do not contend otherwise.[96] Accordingly, Sellers did not inform Buyers that the Company would not have the opportunity to bid on those parts.[97] Rather, Sellers had communicated to Buyers that they believed the Company would have the opportunity to bid on the Lost Parts.[98] Had Buyers known that the Company lost that opportunity, "if [Buyers] would have chosen to continue at all, [Buyers] would have reduced [their] price."[99]

         E. Litigation Ensues.

         Dissatisfied with the Company's inability to re-bid on the Lost Parts, Buyers decided to take action. On April 5, 2017, Accurus asserted a Direct Claim against Sellers.[100] In the Direct Claim, Accurus claimed losses from Sellers' alleged breaches of the APA that exceeded the amount of funds remaining in the Indemnity Escrow Fund, and demanded that the Indemnity Escrow Fund remain with the Escrow Agent pending resolution of the Direct Claim.[101]

         Julius then sought relief in this Court. Julius filed his initial Complaint on September 1, [102] and an Amended Complaint on September 26.[103] In Counts I through IV of the Amended Complaint, Sellers seek a declaratory judgment that Accurus breached the Escrow Agreement and the APA, as well as specific performance of the Escrow Agreement or, in the alternative, a mandatory injunction for breach of the APA.[104] In Count V, Sellers allege Buyers breached the implied covenant of good faith and fair dealing by withholding the escrowed funds and asserting invalid indemnification claims.[105] On October 11, Buyers filed a counterclaim against Sellers, alleging they overpaid for ZTM's assets.[106] Buyers' counterclaim alleges a single count of breach of the APA, and is specifically limited to "the breach of express representations in the APA."[107]

         The litigation proceeded. The parties filed their cross-motions for summary judgment on April 15, 2019 and completed briefing on June 18.[108] I heard oral argument on July 11, [109] and render my decision today. For the following reasons, I grant in part and deny in part both Sellers' and Buyers' motions.

         II. ANALYSIS

         On their cross-motions for partial summary judgment, the parties ask me to determine the issue of liability on all counts asserted by Sellers and Buyers.[110] Summary judgment is appropriate where there is no genuine dispute of material fact and the moving party is entitled to judgment as a matter of law.[111]

Where the parties have filed cross motions for summary judgment and have not presented argument to the Court that there is an issue of fact material to the disposition of either motion, the Court shall deem the motions to be the equivalent of a stipulation for decision on the merits based on the record submitted with the motions.[112]

         In cases involving questions of contract interpretation, like this one, courts will grant summary judgment in two scenarios: (1) when the contract is unambiguous, or (2) when the extrinsic evidence fails to create a triable issue of material fact.[113] In "[s]ummary judgment is the proper framework for enforcing unambiguous contracts because there is no need to resolve material disputes of fact."[114]

         This matter is suited for resolution on the record presented at the summary judgment stage. The parties agree that there are no genuine disputes of material fact and that the APA and Escrow Agreement are clear and unambiguous.[115]Consequently, I resolve this issue on narrow grounds, looking only to the language of the agreements between the parties.

         The parties have struggled over whether the projections are part of the APA and whether Buyers disclaimed reliance on the projections by way of the APA's integration clause.[116] Sellers have consistently argued that the projections have no bearing on the outcome of this matter. Buyers' position has been more nuanced and has evolved throughout the duration of the dispute.[117] Buyers eventually conceded that the allegedly inaccurate sales projections are not part of the APA, asserting they are evidence of Sellers' breach.[118] In keeping with Buyers' framing of the issue, I do not consider the projections beyond their significant role in the factual background. I need only determine whether Sellers represented that Buyers would undoubtedly have the opportunity to bid on the Lost Parts under the APA's plain and unambiguous terms.

         I conclude that Sellers did not breach the terms of the APA and therefore are entitled to partial summary judgment on Buyers' Counterclaim. I also conclude that Buyers did not breach the Escrow Agreement or implied covenant of good faith and fair dealing and are entitled to partial summary judgment on Counts I through V of Sellers' Amended Complaint.

         A. Sellers Are Entitled To Partial Summary Judgment On Buyers' Counterclaim.

         According to Buyers, Sellers breached Sections 3.25(a), 3.25(d), 3.28, and 3.7(a) of the APA by failing to notify Buyers that (1) Boeing had awarded the Lost Parts to other suppliers in 2013 and 2014 and (2) therefore, Accurus did not have the opportunity to bid on the Lost Parts. Buyers contend that, pursuant to the APA, they "were purchasing, among other assets, [] the opportunity to bid to renew the Lost Parts"[119] and that "the opportunity to re-bid on [the Lost Parts] was addressed within the representations and warranties" in the APA.[120]

         Because this case involves questions of contract interpretation, I look to the language of the APA to determine whether summary judgment is appropriate.

The principles governing contract interpretation are well settled. Contracts must be construed as a whole, to give effect to the intentions of the parties. Where the contract language is clear and unambiguous, the parties' intent is ascertained by giving the language its ordinary and usual meaning. Courts consider extrinsic evidence to interpret the agreement only if there is an ambiguity in the contract.[121]

         "When interpreting a contract, a court must give effect to all of the terms of the instrument and read it in a way that, if possible, reconciles all of its provisions."[122] "[A] court will prefer an interpretation that harmonizes the provisions in a contract as opposed to one that creates an inconsistency or surplusage."[123] "Contract terms themselves will be controlling when they establish the parties' common meaning so that a reasonable person in the position of either party would have no expectations inconsistent with the contract language."[124]

         Contracting parties allocate risk through representations and warranties.[125]Delaware courts "respect the ability of sophisticated businesses . . . to make their own judgments about the risk they should bear and the due diligence they undertake, recognizing that such parties are able to price factors such as limits on liability."[126]Consistent with Delaware's pro-contractarian policy, "a party may not come to court to enforce a contractual right that it did not obtain for itself at the negotiating table."[127] Delaware law presumes parties are bound by the language of the agreement they negotiated, especially when the parties are sophisticated entities that have engaged in arms-length negotiations.[128]

         With these principles in mind, I look only to the plain language of the APA's representations or warranties to determine whether the parties accounted for the risk of unknown and undisclosed lost parts. Here, Buyers' bargained-for representations and warranties did not protect them against the risk that they would be unable to bid on the Lost Parts. Nor did the APA impose on Sellers an obligation to notify Buyers about Boeing's decision to award the Lost Parts to other suppliers in 2013 and 2014. Buyers cannot demonstrate Sellers breached the APA, and Sellers are entitled to summary judgment on Buyers' Counterclaim.[129]

         1. Sellers Did Not Breach Section 3.25(d) of the APA Because There Were No "Disputes," "Complaints," or "Issues" With Respect To Boeing And The Lost Parts.

         Buyers argue that the fact that "ZTM no longer had the opportunity to bid to renew the Lost Parts" was a "material issue" that Sellers were obligated to disclose under Section 3.25(d).[130] Section 3.25(d) states: "Seller has disclosed to Buyer any material disputes, complaints, or issues with respect to any customers or suppliers and the manner in which Seller proposes to resolve such disputes, complaints or issues."[131] The parties disagree as to whether the lost opportunity to bid is a material "issue" with Boeing. Because the APA is unambiguous, I discern the parties' intended meaning by giving the term "its ordinary and usual meaning" and reading the APA as a whole.[132]

         Dictionary definitions assist in discerning the usual and ordinary meaning of "issue."[133] Black's Law Dictionary defines "issue" as "a point in dispute between two or more parties."[134] Merriam-Webster defines "issue" as: "a vital or unsettled matter;" a "concern" or "problem;" "a matter that is in dispute between two or more parties;" and "the point at which an unsettled matter is ready for a decision."[135]

         From these definitions, I conclude that the parties intended to adopt the ordinary meaning of "issue," which requires there to have been an actual dispute or question raised by ZTM or Boeing that ZTM or Boeing intended to resolve. This necessarily implies that ZTM or Boeing needed to be aware of a problem-namely Boeing's decision to award the Lost Parts to other suppliers and ZTM's dissatisfaction with that decision-and bring that problem to the attention of the other party for inquiry and resolution, thereby creating an "issue" between Boeing and ZTM.[136]

         Reading the APA as a whole bolsters my interpretation of "issues." The other terms in Section 3.25(d), namely "disputes" and "complaints," reinforce the conclusion that the parties intended to adopt the plain and ordinary meaning of "issues."[137] Black's Law Dictionary defines "dispute" as a "conflict or controversy."[138] Merriam-Webster defines the noun "dispute" as "verbal controversy," "debate," or "quarrel," and defines the verb as "to call into question or cast doubt upon," "struggle against," "oppose," or "contend over."[139] Further, Merriam-Webster defines "complaint" as an "expression of grief, pain, or dissatisfaction" or "something that is the cause or subject of protest or outcry."[140]Similar to the definitions of "issue," the definitions of "dispute" and "complaint" require there be an active controversy of which both parties are or become aware.

         Buyers eschew the plain meaning of "issues" and argue for a broader reading. Buyers contend I should not interpret "issues" in a way that harmonizes it with "disputes" and "complaints," arguing that "defining an agreed-upon contractual term as a redundancy violates the established canon of contract interpretation that a contract should not be read to render terms superfluous."[141] "While redundancy is sought to be avoided in interpreting contracts, this principle of construction does not go so far as to counsel the creation of contract meaning for which there is little or no support in order to avoid redundancy."[142] My interpretation reflects conservative verbosity, not improper redundancy. "Issue" itself is defined in terms of a "dispute between two or more parties."[143] Both "issue" and "complaint" imply a "concern" or "problem" existing "between two or more parties"[144] that has risen to a "conflict or controversy."[145] Although the Court prefers to avoid surplusage when interpreting a contract, I decline to dismiss the plain and ordinary meaning of "issues" to achieve that goal.

         Prior to the sale of the Company, Sellers identified and actively responded to a lost opportunity to bid on 44 parts valued at approximately $2 million in sales, which is less than the $3.3 million in sales in 2015 for the Lost Parts.[146] The 2015 lost opportunity became an "issue" between Boeing and ZTM. ZTM actively sought the opportunity to bid on parts, and Boeing responded with RFQs indicating that ZTM lost the opportunity to bid on certain parts. Shortly thereafter, ZTM took immediate steps to secure the opportunity to re-bid. In that scenario, ZTM became aware of a loss that created a "vital or unsettled matter" with Boeing.[147] This nuance does not compel a finding that every lost opportunity is an "issue."

         The facts surrounding the Lost Parts are distinct. No "issue" arose when Boeing awarded the Lost Parts to other suppliers and ZTM lost the opportunity to bid on those parts. Neither Boeing nor ZTM raised any problem or made any inquiry about the Lost Parts when Boeing awarded those parts to other suppliers in 2013 and 2014. Buyers offer no evidence that Boeing alerted ZTM that the Lost Parts were awarded to other suppliers in 2013 or 2014, or that such an alert became a "matter [] in dispute"[148] between the parties. ZTM was not aware of a loss that became a "vital or unsettled matter"[149] in ZTM's relationship with Boeing. In 2013 and 2014, ZTM had no occasion to respond to Boeing's decision to award the Lost Parts to other suppliers, raise for Boeing's consideration the question of whether ZTM would be able to re-bid on the Lost Parts, or actively pursue the opportunity to re-bid on the Lost Parts. ZTM did not know that it had lost that opportunity.

         The fact that Boeing awarded the Lost Parts to other suppliers is not, by itself, evidence of a dispute, complaint, or issue between ZTM and Boeing. ZTM and Boeing had an LTA, and it was typical for parts to be added to or removed from that LTA. Buyers have not demonstrated that awarding parts to other suppliers was the result of, or resulted in, any disagreement between Boeing and ZTM.

         Rather, after Boeing awarded the Lost Parts to other suppliers, ZTM and Boeing continued their business relationship without any dispute until Accurus voiced its concerns after Closing. In a June 2016 letter to Boeing, Jim Gibson, then-President of Accurus, recognized ZTM's "good standing with The Boeing Company."[150] One month before the parties signed the APA, Boeing sent ZTM three award letters awarding ZTM additional parts to manufacture.[151] After the Closing, Boeing renewed its contracts for "most of the parts set to expire in 2016 for which [Accurus] had the opportunity to bid."[152]

         When the parties signed the APA, Boeing and ZTM had a good working relationship and had no disputes, issues, or complaints between each other, under the plain meaning of these terms. Thus, Sellers did not breach Section 3.25(d) by failing to disclose Boeing's decisions to move the Lost Parts to another supplier.

          2. Sellers Did Not Breach Sections 3.25(a) And 3.7(a) Of The APA Because Those Sections Only Apply To Events That Occurred After December 31, 2015, And Boeing Awarded The Lost Parts To Other Suppliers In 2013 and 2014.

         Buyers also allege that Sellers breached Sections 3.25(a) and 3.7(a) of the APA. In particular, Buyers argue that by awarding the Lost Parts to other suppliers, Boeing materially changed or reduced its business relationship with ZTM under Section 3.25(a), and that Boeing's choice to award the Lost Parts to other suppliers and the Company's consequent inability to bid on those parts constituted a Material Adverse Effect under Section 3.7(a). Buyers have failed to demonstrate that Sellers breached the APA under the plain meaning of both Sections.

         Both Sections contain dispositive temporal cutoffs. Section 3.25(a) states:

Since [December 31, 2015], no customer, distributor, or supplier of the Business has terminated or materially reduced or altered its business relationship with Seller or Seller Subsidiary or materially changed the terms on which it does business with either, or threatened that it intends to cancel, terminate, or otherwise materially reduce or alter its business relationship with either.[153]

         Section 3.7(a) states:

Since [December 31, 2015], the Seller Group has conducted its operations in the ordinary and usual course of business consistent with past practice, and there has not been any: (a) event, occurrence, or development that has had, or reasonably could be expected to have, individually or in the aggregate, a Material Adverse Effect.[154]

         Sections 3.25(a) and 3.7(a) are both representations about events or occurrences occurring after the Balance Sheet Date of December 31, 2015. Anything that occurred before the Balance Sheet Date cannot form the basis of Buyers' claims under either Section 3.25(a) or 3.7(a). ZTM lost the opportunity to bid on the Lost Parts before that time. Boeing awarded the Lost Parts to other suppliers in 2013 and 2014. Losing the opportunity to bid on the Lost Parts did not amount to a breach of either Section 3.25(a) or 3.7(a).

         Buyers contend the Balance Sheet Date has no bearing on my analysis. Buyers contend the lost opportunity to bid is tethered to the dates Boeing could have sent ZTM RFQs for the Lost Parts, December 31, 2015 through June 3, 2016, rather than the earlier date on which Boeing decided not to give ZTM the opportunity to bid.[155] With respect to Section 3.25(a), Buyers argue "the relevant period is the time of contracting in June 3, 2016, the date of signing the APA."[156] Buyers rely on Taylor's testimony that "the fundamental asset[] purchased was the right to be able to renew and compete to renew parts when they expired;"[157] on the fact that "[a]fter the manufacturing right for a specific part 'expired,' it could either be renewed or awarded to another supplier;"[158] and on the reality that "the RFQ for a part could be sent close in time to the expiration date."[159] Buyers conclude that as of the date of contracting, and after the Balance Sheet Date, Boeing had materially reduced or altered its relationship with ZTM by failing to issue RFQs for the Lost Parts.[160]

         Similarly, under Section 3.7(a), Buyers argue that "the loss of the opportunity to bid to renew the Lost Parts constituted a Material Adverse Effect after the Balance Sheet Date"[161] "because after December 31, 2015, they should have received RFQs for the Lost Parts, or understood that the lack of an RFQ signaled that the parts were awarded to other manufacturers."[162] According to Buyers, ZTM's failure to receive RFQs for the Lost Parts or follow up with Boeing to determine their status (as ZTM did in 2015 for other lost parts) rendered the lost opportunity to bid a "live issue after December 31, 2015"[163] that "could reasonably be expected" to have a Material Adverse Effect.[164]

         I assume for purposes of this analysis that losing the opportunity to bid on the Lost Parts amounted to a material reduction in ZTM's relationship with Boeing, or a Material Adverse Effect.[165] Even so, I conclude ZTM did not breach Sections 3.25(a) and 3.7(a) because the triggering event occurred before the Balance Sheet Date. Boeing conclusively eliminated ZTM's opportunity to bid on the Lost Parts when it awarded the Lost Parts to other suppliers in 2013 and 2014. Boeing could not have sent ZTM an RFQ for the Lost Parts before December 31, 2015, because Boeing had already awarded those parts to other suppliers. Buyers have not demonstrated that Boeing took any adverse action related to the Lost Parts after December 31, 2015, and before either the execution of the APA on June 3, 2016 or the Closing on July 28, 2016.

         Under Section 3.25(a), there was no material reduction in the Company's business since December 31, 2015 because Boeing awarded the Lost Parts to other distributors prior to that date. Under Section 3.7(a), there was no event, occurrence, or development since December 31, 2015 that could be considered a Material Adverse Effect because the Lost Parts were allocated to another supplier before that date.[166] Buyers cannot establish Sellers breached Sections 3.25(a) and 3.7(a) of the APA.

         3. Sellers Did Not Breach Section 3.28 Of The APA Because Sellers' Representations And Warranties Did Not Contain Any Untrue Or Misleading Statement Of Material Fact With Respect To The Lost Parts.

         Buyers argue that the alleged breaches of Section 3.25(a), 3.25(d), and 3.7(a) are also breaches of Section 3.28. Section 3.28 is a catch-all provision that states:

No representation or warranty made by Seller in this Agreement and no statement contained in the Disclosure Schedule to this Agreement or any certificate or other document furnished or to be furnished to Buyer pursuant to this Agreement, including the other Transaction Documents, contains any untrue statement of a material fact, or omits to state a material fact necessary to make the statements contained therein, in light of the circumstances in which they are made, not misleading.[167]

         Under the plain terms of the APA, Sellers explicitly represented and warranted that they disclosed all material issues with Boeing to Buyers; that Boeing had not materially altered or reduced its business relationship with ZTM since the Balance Sheet Date; that no Material Adverse Effect occurred after the Balance Sheet Date; and that none of the representations and warranties contain untrue statements of material fact.

         Sellers made these representations and warranties truthfully at the time of contracting. As discussed at length above, the lost opportunity to bid on the Lost Parts was not an "issue" that required disclosure under Section 3.25. Likewise, that loss was not a material reduction in ZTM's business or Material Adverse Effect that occurred since the Balance Sheet Date. Because Sellers did not breach Sections 3.25(a), 3.25(d), or 3.7(a), Buyers cannot prevail under Section 3.28.

         Those predicate sections failed to shift to Sellers any risk that Accurus would not have the opportunity to bid on the Lost Parts. Sections 3.25(a), 3.25(d), 3.28, and 3.7(a) do not contain any representations or warranties that required Sellers to notify Buyers that Boeing had awarded the Lost Parts to other suppliers in 2013 or 2014, or that guaranteed Buyers would have the opportunity to bid on the Lost Parts at the time of sale. Buyers cannot now rely on the APA's catchall provision "to enforce a contractual right that it did not obtain for itself at the negotiating table."[168]

         Buyers recognize that representations and warranties "serve an important risk allocation function."[169] Sellers informed Buyers that the Lost Parts were expiring in 2016. Sellers also informed Buyers of Sellers' sincere, yet unsubstantiated, belief that "the opportunity to quote [the Lost Parts] would come"[170] and that "those parts [the Lost Parts] were available to be bid on."[171] Yet, Buyers failed to protect the uncertain future of the Lost Parts in the APA. If preserving opportunities to bid on potentially lost parts was so valuable to Buyers, they could have bargained for explicit protections against lost opportunities. They failed to do so. Taylor, who led the APA negotiations for Buyers, confirmed he never requested that the APA include any protection against the possibility that the Lost Parts would not be renewed after calendar year 2016.[172] By failing to negotiate for contractual protections related to the Lost Parts, Buyers bore the full risk of loss.

         4. Buyers Are Not Entitled To Indemnification Under Section 8.3(a) Of The APA Because Sellers Did Not Breach Sections 3.25(a), 3.25(d), 3.28, And 3.7(a).

         Buyers contend they are entitled to indemnification under Section 8.3(a) of the APA. Buyers are correct that Sellers are required to indemnify Buyers for breaches representations and warranties under the plain language of Section 8.3(a).[173] Because Sellers did not breach the APA's representations and warranties, Buyers are not entitled to indemnification under Section 8.3(a).

         B.Buyers Are Entitled To Partial Summary Judgment On Counts I Through V Of Sellers' ...


Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.